Construction Budget Guide: Class the Estimate First
A construction budget fails when a screening figure is treated as authorization. On a base of 100, the wider Class 5 ends are 50 and 200. The wider Class 3 ends are 80 and 130.
Read guideStart with the current budget guide to separate construction costs, owner costs and uncertainty.
Review budget components, estimate maturity and cost decisions at design checkpoints.
3 guides in this topic.
A construction budget fails when a screening figure is treated as authorization. On a base of 100, the wider Class 5 ends are 50 and 200. The wider Class 3 ends are 80 and 130.
Read guide
Read the NAHB 2024 survey by denominator: sales price versus construction cost, fees already inside site work, and a blank cell for the quote.
Read guide
What a construction budget should include, how estimates mature with design, and how to manage cost at each design checkpoint before commitments are made.
Read guideFor a process-industry estimate, class the estimate before treating the total as a budget. After reviewing the budget, use Project Planning’s risk checklist to assign responsibility for unresolved items.